ISTQB Sample Questions Set - 8



1.    A formal assessment of a work product conducted by one or more qualified independent reviewer to detect defects.
A.    Inspection.
B.    Walkthrough.
C.    Review
D.   Non Conformance
2.    Test Case are grouped into Manageable (and scheduled) units are called as
A.    Test Harness
B.    Test Suite
C.    Test Cycle
D.   Test Driver
3.    Configuration and compatibility testing are typically good choices for outsourcing
A.    True
B.    False
4.    What type of tools to be used for Regression Testing
A.    Performance
B.    Record/Playback
C.    A. & B.
D.   None
5.    System Integration testing should be done after
A.    Integration testing
B.    System testing
C.    Unit testing
D.   Component integration testing
6.    During this event the entire system is tested to verify that all functional information structural and quality requirements have been met. A predetermined combination of tests is designed that when executed successfully satisfy management that the system meets specifications
A.    Validation Testing
B.    Integration Testing
C.    User Acceptance Testing
D.   System Testing
7.    What is the normal order of activities in which software testing is organized?
A.    Unit, integration, system, validation
B.    System, integration, unit, validation
C.    Unit, integration, validation, system
D.   None of the above
8.    The goal of a software tester is to find bugs, find them as early as possible and make sure they get fixed.
A.    True
B.    False
9.    Beta testing is performed at developing organization's site where as Alpha testing is performed by people at their own locations.
A.    True
B.    False
10.                       The principal attributes of tools and automation are
A.    Speed & efficiency
B.    Accuracy & precision
C.    All of the above
D.   None of the above
11.                       In ______ testing doesn't know anything about the sofware being tested; it just clicks or types randomly.
A.    Random testing
B.    Gorilla testing
C.    Adhoc testing
D.   Dumb monkey testing
12.                       A series of probing questions about the completeness and attributes of an application system is called
A.    Checklist
B.    Checkpoint review
C.    Decision table
D.   Decision tree
13.                       The testing technique that requires devising test cases to demonstrate that each program function is operational is called
A.    Black-box testing
B.    Glass-box testing
C.    Grey-box testing
D.   White-box testing
14.                       A white box testing technique that measures the number of or percentage of decision directions executed by the test case designed is called
A.    Condition coverage
B.    Decision/Condition coverage
C.    Decision Coverage
D.   Branch coverage
15.                       Which summarizes the testing activities associated with one or more test design specifications.
E.    Test Summary report
F.     Test Log
G.   Test Incident Report
H.   Test Script
16.                       Testing with out a real plan and test cases is called ---
A.    Gorilla testing
B.    Monkey testing
C.    Adhoc testing
D.   All of the above
17.                       Which rule should not be followed for reviews
A.    Defects and issues are identified and corrected
B.    The product is reviewed not the producer
C.    All members of the reviewing team are responsible for the result of the review
D.   Each review has a clear predefined objective
18.                       Verification can be termed as 'Are we building the product right?"
A.    True
B.    False
19.                       Which testing is used to verify that the system can perform properly when internal program or system limitations have been exceeded
A.    Stress Testing
B.    Load Testing
C.    Performance Testing
D.   Volume testing
20.                       Defects are recorded into three major purposes. They are:
a.       To correct the defect
b.      To report status of the application
c.       To improve the software development process
                                                          A.      True
                                                          B.      False
1
2
3
4
5
6
7
8
9
10
A
B
A
B
C
C
A
A
B
C
11
12
13
14
15
16
17
18
19
20
D
A
C
B
A
D
C
A
A
A