ISTQB Sample Questions Set - 6


1.    The Switch is switched off once the temperature falls below 18 and then it is turned on when the temperature is more than 21. When the temperature is more than 21. Identify the Equivalance values which belong to the same class.
A.    12,16,22
B.    24,27,17
C.    22,23,24
D.   14,15,19
2.    What is an equivalence partition (also known as an equivalence class)?
A.    A set of test cases for testing classes of objects
B.    An input or output range of values such that only one value in the range becomes a test case
C.    An input or output range of values such that each value in the range becomes a test case
D.   An input or output range of values such that every tenth value in the range becomes a test case.
3.    Which of the following is not a part of the Test Implementation and Execution Phase
A.    Creating test suites from the test cases
B.    Executing test cases either manually or by using test execution tools
C.    Comparing actual results
D.   Designing the Tests
4.    Link Testing is also called as :
A.    Component Integration testing
B.    Component System Testing
C.    Component Sub System Testing
D.   Maintenance testing
5.    Who are the persons involved in a Formal Review :-
i. Manager
ii. Moderator
iii. Scribe / Recorder
iv. Assistant Manager
A.    i,ii,iii,iv are true
B.    i,ii,iii are true and iv is false.
C.    ii,iii,iv are true and i is false.
D.   i,iv are true and ii, iii are false.
6.    Which of the following statements regarding static testing is false:
A.    Static testing requires the running of tests through the code
B.    Static testing includes desk checking
C.    Static testing includes techniques such as reviews and inspections
D.   Static testing can give measurements such as cyclomatic complexity
7.    Designing the test environment set-up and identifying any required infrastructure and tools are a part of which phase
A.    Test Implementation and execution
B.    Test Analysis and Design
C.    Evaluating the Exit Criteria and reporting
D.   Test Closure Activities
8.    A Type of functional Testing, which investigates the functions relating to detection of threats, such as virus from malicious outsiders.
A.    Security Testing
B.    Recovery Testing
C.    Performance Testing
D.   Functionality Testing
9.    A Person who documents all the issues, problems and open points that were identified during a formal review.
A.    Moderator.
B.    Scribe
C.    Author
D.   Manager
10.                       The Test Cases Derived from use cases
A.    Are most useful in uncovering defects in the process flows during real world use of the system
B.    Are most useful in uncovering defects in the process flows during the testing use of the system
C.    Are most useful in covering the defects in the process flows during real world use of the system
D.   Are most useful in covering the defects at the Integration Level
11.                       One of the fields on a form contains a text box which accepts alpha numeric values. Identify the Valid Equivalence class
A.    BOOK
B.    Book
C.    Boo01k
D.   book
12.                       In a Examination a candidate has to score minimum of 24 marks inorder to clear the exam. The maximum that he can score is 40 marks. Identify the Valid Equivalance values if the student clears the exam.
A.    22,23,26
B.    21,39,40
C.    29,30,31
D.   0,15,22
13.                       Verification involves which of the following :-
i. Helps to check the Quality of the built product
ii. Helps to check that we have built the right product.
iii. Helps in developing the product
iv. Monitoring tool wastage and obsoleteness.
A.    Options i,ii,iii,iv are true.
B.    i is true and ii,iii,iv are false
C.    i,ii,iii are true and iv is false
D.   ii is true and i,iii,iv are false.
14.                       A Project risk includes which of the following :
A.    Organizational Factors
B.    Poor Software characteristics
C.    Error Prone software delivered.
D.   Software that does not perform its intended functions
15.                       Which of the following is a Key Characteristics of Walk Through
A.    Scenario , Dry Run , Peer Group
B.    Pre Meeting Preparations
C.    Formal Follow Up Process
D.   Includes Metrics
16.                       Which of the following techniques is NOT a White box technique?
A.    Statement Testing and coverage
B.    Decision Testing and coverage
C.    Condition Coverage
D.   Boundary value analysis
17.                       Reporting Discrepancies as incidents is a part of which phase :-
A.    Test Analysis and Design
B.    Test Implementation and execution
C.    Test Closure Activities
D.   Evaluating exit criteria and reporting
18.                       In a risk-based approach the risks identified may be used to :
i. Determine the test technique to be employed
ii. Determine the extent of testing to be carried out
iii. Prioritize testing in an attempt to find critical defects as early as possible.
iv. Determine the cost of the project
A.    ii is True; i, iii, iv & v are False
B.    i,ii,iii are true and iv is false
C.    ii & iii are True; i, iv are False
D.   ii, iii & iv are True; i is false
19.                       Incidents would not be raised against:
A.    Requirements
B.    Documentation
C.    Test cases
D.   Improvements suggested by users
20.                       The Planning phase of a formal review includes the following :-
A.    Explaining the objectives
B.    Selecting the personnel, allocating roles.
C.    Follow up
D.   Individual Meeting preparations
1
2
3
4
5
6
7
8
9
10
C
B
D
A
B
A
B
A
B
A
11
12
13
14
15
16
17
18
19
20
C
C
B
A
A
D
B
B
D
B